What the guide actually is

The Gec Alsthom Protective Relays Application Guide is a technical reference document that covers the selection, setting calculation, and coordination methodology for a range of protective relay products from what was originally GEC Alsthom and later became part of the GE Power & Water portfolio. It is not a replacement for the product-specific installation manual. It is a bridge document meant to help engineers work out reasonable starting parameters before they open the relay configuration software.

I have spent years looking at settings files on these units, and the guide has a specific place in that workflow. You use it to avoid the most obvious mistakes during the first cut of a coordination study. The setting ranges it lists for overcurrent, earth fault, and differential elements are derived from the relay's internal algorithm limits and the typical CT classes that match those applications. Where most people go wrong is treating the guide as authoritative. It is not. It gives you directions, not decisions. The actual protection philosophy for a given bay depends on the network studies, the fault level data, and the coordination requirements that your client or regional operator has already defined. The guide will not tell you whether to use a definite time or an inverse curve for a specific breaker. It will show you the available curves and the math behind them.

When the guide is useful and when it is not

The guide is useful when you need to quickly narrow down a relay model for a new feeder or transformer protection scheme. It lists the available element types, the permissible CT ratios, and the general calculation approach for pick-up and time dial settings. If you are doing a routine 11 kV or 33 kV distribution coordination exercise, the examples in the guide match those scenarios closely enough to be practical. It becomes less useful when you are dealing with generator protection, busbar differential, or motor protection where the fault current characteristics are non-standard. The guide assumes balanced system conditions and does not cover every edge case involving inverter-based resources or series-compensated lines. If your project involves those, you should plan on spending extra time with the factory settings documentation and possibly running EMTP or PSCAD simulations to verify the relay behavior.

Setting calculation approach

The guide walks through the setting calculation process in a straightforward manner. You start with the maximum and minimum fault currents at the point of protection. You select a CT ratio that keeps the secondary current within the relay's measurable range under both conditions. Then you calculate the overcurrent element pick-up so that it sits above the maximum load current with an appropriate margin, typically 1.2 to 1.5 times the rated load current depending on whether you are protecting a transformer or a feeder. For inverse time curves, the guide shows how the time dial factor interacts with the curve exponent. A standard IDMT curve will operate faster at higher multiples of pick-up. The time dial is not just a speed knob. It shifts the entire curve, and the interaction with the curve type matters more than most engineers realize. If you switch from a standard inverse to an extremely inverse curve without adjusting the time dial, your coordination margins can change significantly in the low fault current region where earth fault elements usually operate. Here is one thing the guide does not emphasize enough. The relay's actual operating time includes the CT saturation effect and the relay's internal filtering delay. When you are coordinating across multiple voltage levels, the total delay stack adds up. A 0.2 second CT transient plus a 0.1 second relay delay plus the time dial increment means you need to build in at least a 0.4 to 0.5 second margin between adjacent overcurrent stages for reliable discrimination. Anything less and you will see nuisance tripping during external faults when the CTs are not perfectly matched.

Get the Full Details

(PDF) GEC ALSTHOM PROTECTIVE RELAYS Application Guide
(PDF) GEC ALSTHOM PROTECTIVE RELAYS Application Guide

A realistic problem I ran into

I was working on a 33 kV substation upgrade where the existing protection scheme used older GEC Alsthom units and a new section was being added with updated relays. The original settings from the old study had an earth fault element set at 0.15 per unit with a time dial of 0.6. When I reviewed the coordination with the new relay, the fault current at the remote end was lower than expected because the utility had reinforced the upstream network. The old time dial no longer provided sufficient discrimination. I recalculated the setting using the application guide method and landed on a time dial of 0.9 with the same pick-up. That added about 0.35 seconds to the earth fault element operation time at the lowest fault level, which restored proper coordination with the upstream fuse. The workaround was not complex, but it required me to verify the actual fault level at the remote end rather than trusting the legacy study values. The old file had assumed a higher fault current, which is why the original setting looked correct on paper but failed in the field review. This kind of mismatch is more common than you would think when a network has been upgraded over a decade.

Common pitfalls

One frequent mistake I see is using the guide's example CT ratios without checking the physical CTs on site. The relay might accept a different ratio than the one in the book example, and programming the wrong ratio shifts every calculated setting. Always verify the nameplate CT ratio before entering anything into the relay. Another issue is ignoring the relay's input range for voltage elements. The guide lists typical VT ratios, but if your system uses an ungrounded or resonant grounded configuration, the residual voltage element behavior is different from a solidly grounded system. The pickup and time settings for ground fault protection must account for the zero-sequence voltage available during a single line to ground fault, and that value varies widely depending on your neutral grounding method.

What the guide cannot do for you

The guide will not perform the coordination study for you. It does not generate a time-current curve plot that you can hand to a utility reviewer. You need external software for that, and the guide acknowledges this by referring you to the recommended tools. In practice, many engineers use ETAP, DIgSILENT, or PSCAD for the detailed coordination work and reference the guide for the relay-specific setting formulas. There is also the matter of firmware versions. The relay models covered in the guide span several generations, and the internal algorithms changed between firmware releases. If you are working with a P641 or a similar feeder protection relay, the setting calculation may differ slightly depending on whether the unit is running an older firmware or the latest available version. The guide gives general guidance but cannot cover every firmware-specific nuance.

Protective relays application guide: GEC Measurements: Amazon.com: Books
Protective relays application guide: GEC Measurements: Amazon.com: Books

Practical advice from experience

When you are using the guide to develop initial settings, always cross-check the calculated time dial against a simple spreadsheet that computes the operating time at both minimum and maximum fault levels for each element. This takes about ten minutes and catches most obvious errors before you download the settings file to the relay. The guide's own examples do not always show this verification step clearly. I also recommend keeping a copy of the latest factory-setting table alongside the guide. The factory table has the actual permissible ranges for every element, including any restrictions that apply to specific hardware configurations. The guide summarizes this information, but the factory table is the source of truth when there is a discrepancy.

Accessing the guide

The guide is typically distributed through the manufacturer's technical literature portal or through authorized distributors. It is not a publicly available free document in the same way that some introductory white papers are. If you are contacting the technical support team, request the version that matches your relay model and the regional edition, since some settings conventions vary by market. The document itself is usually around 80 to 120 pages depending on the edition. It contains calculation worksheets, curve selection tables, and example scenarios for common protection schemes. The worksheets are in a format that you can reproduce in a spreadsheet, which is often more convenient than working from the printed pages during an active coordination exercise.

Bottom line

The Gec Alsthom Protective Relays Application Guide is a practical reference for engineers who need to move from a protection concept to a first-cut settings file. It will not replace a full coordination study or the product installation manual. It is most effective when used alongside site-specific fault level data, verified CT ratios, and a software tool for time-current curve plotting. If you treat it as a starting point rather than a final authority, it saves time and reduces the likelihood of the kind of coordination issues I described earlier. For projects with non-standard systems, inverter-based generation, or complex multi-source networks, plan on supplementing the guide with dedicated simulation work and direct engagement with the manufacturer's application engineering team. The guide covers the common cases well. The uncommon cases require additional effort.

Protective Relays Application Guide: General Electric Company: 9780927510257: Amazon.com: Books
Protective Relays Application Guide: General Electric Company: 9780927510257: Amazon.com: Books